When Wero Whitewater Park built a 16-metre, three-level climbing structure with 78 elements, large timber obstacles had to be secured at height between steel frames where standard access wasn't possible. Working under Clyde Services alongside the German KristallTurm team, our two-person rope access crew combined crane lifts and rigging to install every obstacle safely over three weeks. The facility opened in July 2025 as New Zealand's tallest multi-level climbing course — and proved Geo Mana delivers structural installation at height.
The challenge
What made this difficult
A 16-metre climbing structure was being built at Wero Whitewater Park in South Auckland — a three-level KristallTurm design carrying 78 climbing elements. Many of the obstacles and large timber components had to be positioned and secured at height between steel structures, where standard access was not an option. Working under Clyde Services, the crane company on the build, our crew was brought in to make those installs happen safely.
Specific issues
Large timber obstacles needed to be lifted and secured between steel structures at height
Working at heights up to 16 metres across three levels of the structure
Coordination required between the rope access crew, Clyde Services crane operators, and the German KristallTurm installation team
A new type of project for the crew, requiring adaptability on the job
The response
- 01
Provided rope access and rigging support for installing and securing climbing obstacles across all three levels
- 02
Worked under Clyde Services alongside their crane operators and the German KristallTurm installation team
- 03
Used a combination of crane lifts and rope access to position large timber elements safely between the steel framework
- 04
Two-person Geo Mana crew delivered consistently across a three-week programme
Spec snapshot
The numbers on record
- 01Structure height: 16 metres across three levels
- 02Climbing elements installed: 78
- 03Programme: approximately three weeks (May 2025 install)
- 04Delivery team: two-person rope access crew working with crane operators and the manufacturer's three-person installation team
The outcome
Work that holds up.
All obstacles were installed and secured safely across the full 16-metre structure, with every timber element positioned between the steel framework through a combination of crane lifts and rope access. The two-person crew worked consistently across the three-week programme, coordinating with Clyde Services' crane operators and the German KristallTurm installation team. The facility opened in July 2025 as New Zealand's tallest multi-level climbing course, built to hold up to 100 climbers at a time. For Geo Mana, the project proved the team's ability to deliver structural installation at height — a new capability for the business.
- Rope access
- Crane operations
- Rigging at height
- Structural installation
- Multi-team coordination
From the face
How it looked on site
Actual project photography








Your ground
Facing something similar?
Send the location, a few photos and any engineering information you have. We will tell you the practical next step.
Discuss a project
021 187 8118